- Westfield River Basin – Notice of Application for a Water Management Act Permit Renewal (pdf) – 5 renewal applications – posted 12/23/15
- Northampton – Notice of Application for a 401 Water Quality Certificate (pdf) – lining of a culvert carrying Pine Brook under Route 5, Interstate 91 and the Knowledge Corridor Rail Tracks – posted 12/23/15
- Granby – Definitive Subdivision/K-Pine Estates Phase 2 – ENF – comments due 12/14/15
- Belchertown – Belchertown State School Redevelopment Project – Draft EIR- Comments due 12/23/2015
- Brimfield – Notice of Intent to Initiate an Ecological Restoration Project (pdf) – Lake Sherman – posted 12/9/15
- Ludlow – Notice of Public Hearing, re: Vegetation Management Plan (pdf) – Massachusetts Municipal Wholesale Electric Company – comments due 12/23/15
- Springfield – MGM Springfield – Notice of Project Change – Does not require an Environmental Impact Report – posted 11/25/15
- Chicopee – Chicopee Water Department Redundant Water Transmission Main – ENF – Does not require an Environmental Impact Report – 11/18/15
- Northampton – Notice of Intent to Initiate an Ecological Restoration Project (pdf) – Upper Roberts Meadow Reservoir Dam – posted 11/9/15
- Westborough – Notice of Public Hearing, re: Proposed Disposition of Commonwealth Property (pdf) – Possible selling of corner of Milk & Oak Sts – Public Hearing 12/3/15
- Greenfield – Notice of Public Hearing, re: Proposed Disposition of Commonwealth Property (pdf) – Possible selling of 62 Newell Pond Rd – Public Hearing 12/2/15
- Belchertown – culvert crossing on Blue Meadow Road – Notice of Application for a 401 Water Quality Certification (pdf) – posted 9/9/15
- Goshen – Lower Highland Lake Dam Rehabilition – ENF Certificate – Does not require an Environmental Impact Report – 9/11/15
- Northampton – Roberts Meadow Brook Channell Improvements – ENF Certificate – Does not require an Environmental Impact Report – 9/11/15
- Westfield River Basin – Notice of Availability of Schedule for Preparation of Water Needs Forecasts for Public Water Suppliers with Water Management Act Permits – submitted 8/12/15
- Various locations -Energy Facilities Siting Board – Notice of Public Hearings, re: Northeast Energy Direct Project (pdf) – posted 7/22/2015
- Hawley – Bridge Replacement on Savoy Road over the Chickley River – Notice of Application for a 401 Water Quality Certification (pdf) – posted 7/22/15
- Montague – Turners Falls Power Canal Left Bank Drainage Improvements – ENF Certificate – Does not require an Environmental Impact Report – 7/24/15
- Springfield, Holyoke, Longmeadow – Former Springfield Gas Works/Connecticut River Remediation Project – Certificate ENF – Does not require an Environmental Impact Report – issued 7/10/15
- Greenfield & Montague – Cabot Taps Separation Project – Supplemental EIR – Certificate issued – 6/12/15 – Adequately and properly complies with MEPA
- Agawam – Notice of Draft Operating Permit Renewal (pdf) – Covanta Springfield, LLC – posed 6/10/15
- Holyoke, West Springfield and Westfield – Notice of receipt of (YOP) Yearly Operational Plan (pdf) – comments due 6/5/15
- Agawam, Sandisfield, Tyringham – Connecticut Expansion Project – Certificate FEIR – Adequately and properly complies with MEPA (BEAT is very disappointed with this certificate) – and – Notice of Project Change including draft Article 97 legislation – comments due 5/26/15. This project filed with FERC 7/31/14.
- Colrain – Notice of Application for a 401 Water Quality Certification (pdf) – Bridge Replacement North River at ST 112 Jacksonville Road over the North River – submitted 5/20/15
- Amherst – University of Massachusetts – Notice of Modification to an Individual Reclaimed Water Use Permit (pdf) – submitted 5/6/15
- Sunderland – Sugarbush Meadows (EEA #14183) – Notice of Issuance of a Section 61 Finding (pdf) – submitted 4/22/15
- Hadley – Five College Library Annex – ENF Certificate – 5/8/15 – Does not require an Environmental Impact Report
- West Springfield – K&W Materials and Recycling Facility – ENF Certificate – 5/8/15 – Does not require an Environmental Impact Report
- Fountain Plating Company – Springfield – Notice of Draft Operating Permit Renewal (pdf) – Comments Due 4/24/15
- Northampton – Notice of Application for a 401 Water Quality Certification (pdf) – Upper Roberts Meadow Reservoir Dam Breach & Ecological Restoration Project – submitted 4/8/15
- Stockbridge, West Stockbridge, Lee, Otis, Blanford and Russell – MassDOT Highway Division – Notice of Submisson of a Yearly Operational Plan (pdf) to spray herbicides along roads – comments due 4/10/15
- Deerfield River Basin – Water Withdrawal Permits for Berkshire East and Shelburne Falls Fire District (pdf) – posted 3/25/14
- Ludlow – Massachusetts Municipal Wholesale Electric Company – Notice of receipt of (YOP) Yearly Operational Plan and procedures for public review (pdf) – to apply herbicides – comments due 3/27/15
- Holyoke – City of Holyoke Gas and Electric Department – Notice of Submission of a (YOP) Yearly Operational Plan (pdf) – to apply herbicides – comments due 3/27/15
- Palmer – Proposed Rail Siding – ENF Certificate – Issued 3/6/15 – Does not require an Environmental Impact Report
- Springfield – MGM Springfield – FEIR Certificate – Adequately and properly complies with MEPA – 12/31/14
- Northampton – Paradise Pond Sediment Management Protocol – ENF Certificate – Does not require an Environmental Impact Report – 12/5/14
- Greenfield & Montague – Cabot Taps Separation Project – ENF – – Requires an Environmental Impact Report – 9/5/14
- Belchertown – Belchertown State School Redevelopment Project – ENF – Certificate – Requires an Environmental Impact Report – 6/13/14
return to list of projects or return to top
Definitive Subdivision/K-Pine Estates Phase 2 – Granby
EEA # 15440
Submitted November 23, 2015
Environmental Notification Form (pdf)
Comments due December 14, 2015
For copies: Alan Kotowicz (413) 530-9292
MEPA Analyst: Page Czepiga (617) 626-1021
return to list of projects or return to top
Chicopee Water Department Redundant Water Transmission Main – Chicopee
EEA # 15427
Issued November 18, 2015
Secretary’s Certificate (pdf)
Does not require an Environmental Impact Report
Submitted October 19, 2015
Environmental Notification Form (pdf)
Comments due November 9, 2015
For copies: David Partridge (413) 572-3267
MEPA Analyst: Page Czepiga (617) 626-1021
return to list of projects or return to top
Lower Highland Lake Dam Rehabilition – Goshen
EEA # 15405
Issued September 11, 2015
Secretary’s Certificate (pdf)
Does not require an Environmental Impact Report
Submitted August 12, 2015
Environmental Notification Form (pdf)
Comments due September 1, 2015
For copies: Allen R. Orsi (508) 543-1755
MEPA Analyst: Page Czepiga (617) 626-1021
return to list of projects or return to top
Roberts Meadow Brook Channell Improvements – Northampton
EEA # 15406
Issued September 11, 2015
Secretary’s Certificate (pdf)
Does not require an Environmental Impact Report
Submitted August 12, 2015
Environmental Notification Form (pdf)
Comments due September 1, 2015
For copies: Matthew Taylor (781) 278-5803
MEPA Analyst: Page Czepiga (617) 626-1021
return to list of projects or return to top
Notice of Availability of Schedule for Preparation of Water Needs Forecasts for Public Water Suppliers with Water Management Act Permits – Westfield River Basin
Submitted August 12, 2015
Notice of Availability of Schedule for Preparation of Water Needs Forecasts for Public Water Suppliers with Water Management Act Permits (pdf)
An informational workshop will be held for communities in the Westfield River Basin:
Date: Tuesday, September 15, 2015
Time: 10:00 a.m. to 12:00 p.m.
Location: Holyoke Heritage State Park Exhibit Hall
21 Appleton Street
Holyoke, MA 01040
At the workshop, MassDEP will introduce the WMA permitting process and new regulatory
requirements that may apply to permits, and DCR will review the process for developing a water needs
forecast. All public water systems and communities in the Westfield River Basin are encouraged to
attend this outreach workshop.
The target date for completion of draft water needs forecasts for public water suppliers in these basins
is September 4, 2015. Information that may be useful in developing a draft forecast should be provided
to DCR at the address in the announcement.
return to list of projects or return to top
Turners Falls Power Canal Left Bank Drainage Improvements – Montague
EEA # 15385
Issued July 24, 2015
Secretary’s Certificate (pdf)
Does not require an Environmental Impact Report
Submitted June 24, 2015
Environmental Notification Form (pdf)
Comments due July 14, 2015
For copies: Bruce Griffin (413) 256-0202
MEPA Analyst: Purvi Patel (617) 626-1029
return to list of projects or return to top
Former Springfield Gas Works/Connecticut River Remediation Project – Springfield, Holyoke, Longmeadow
EEA # 15384
Issued July 10, 2015
Secretary’s Certificate (pdf)
Does not require an Environmental Impact Report
Submitted June 10, 2015
Environmental Notification Form (pdf)
Comments due June 30, 2015
For copies: Pamela Chan (978) 392-5309
MEPA Analyst: Purvi Patel (617) 626-1029
return to list of projects or return to top
Cabot Taps Separation Project – Greenfield & Montague
EEA # 15212
Issued June 12, 2015
Secretary’s Certificate (pdf)
Adequately and properly complies with MEPA
Submitted May 6, 2015
Single Environmental Impact Report (pdf)
Comments due June 5, 2015
For copies: MaryEllen Radovanic (508) 792-4500
MEPA Analyst: Alex Strysky (617) 626-1025
return to list of projects or return to top
Five College Library Annex – Hadley
EEA # 15343
Issued May 8, 2015
Secretary’s Certificate (pdf)
Does not require an Environmental Impact Report
Submitted March 25, 2015
Environmental Notification Form (pdf)
Comments now due April 28, 2015
For copies: Richaed Klein (413) 582-7000
MEPA Analyst: Page Czepiga (617) 626-1021
return to list of projects or return to top
K&W Materials and Recycling Facility – West Springfield
EEA # 15349
Issued May 8, 2015
Secretary’s Certificate (pdf)
Does not require an Environmental Impact Report
Site Visit – April 7, 2015 at 2:00 pm
Project Site – 138 Palmer Avenue, West Springfield
Submitted March 25, 2015
Environmental Notification Form (pdf)
Comments due April 14, 2015
For copies: Charlene Perkins (978) 777-7250
MEPA Analyst: Page Czepiga (617) 626-1021
return to list of projects or return to top
Proposed Rail Siding – Palmer
EEA # 15317
Issued March 6, 2015
Secretary’s Certificate (pdf)
Does not require an Environmental Impact Report
Site Visit: February 4, 2015 at 9:00 am
Project Site – 24 3rd Street, Palmer
Submitted January 21, 2015
Environmental Notification Form (pdf)
Comments due February 10, 2015
For copies: Rebecca Williamson (978) 570-2980
MEPA Analyst: Alex Strysky (617) 626-1025
return to list of projects or return to top
EEA # 15282
Issued December 5, 2014
Secretary’s Certificate (pdf)
Does not require an Environmental Impact Report
Submitted November 5, 2014
Environmental Notification Form (pdf)
Comments due November 25, 2014
For copies: Briscoe Lang (401) 334-4100
MEPA Analyst: Purvi Patel (617) 626-1029
return to list of projects or return to top
Connecticut Expansion Project – Sandisfield, Tyringham, Agawam
EEA # 15205
Submitted May 6, 2015
Notice of Project Change
Connecticut Expansion Project – Revised Draft Section 61 Findings and Proposed Article 97 Legislation*
Comments due May 26, 2015*
* BEAT has received a revised version dated May 8 of the Revised Draft Section 61 Findings and Proposed Article 97 Legislation
Issued April 17, 2015
Secretary’s Certificate (pdf)
Adequately and properly complies with MEPA – BEAT is very disappointed. We do not feel that the proponent adequately provided all the relevant environmental information needed for the agencies to base their decisions on.
Submitted March 11, 2015
Final Environmental Impact Report (BEAT has a copy)
Comments due April 10, 2015
Issued November 14, 2014
Secretary’s Certificate (pdf)
Adequately and properly complies with MEPA
Submitted October 8, 2014
Draft Environmental Impact Report
Comments due November 7, 2014
(BEAT has a copy of the 3 volume Report – contact Jane if you would like to view it)
Filed for Expedited Review July 31, 2014
with the Federal Energy Regulatory Commission
Issued July 11, 2014
Secretary’s Certificate (pdf)
Requires an Environmental Impact Report
View BEAT’s comments on the ENF (pdf)
Submitted May 28, 2014
Expanded Environmental Notification Form (pdf)
Comments due June 20, 2014
For copies: Mark Gardella (401) 854-2807
MEPA Analyst: Alex Strysky (617) 626-1025
return to list of projects or return to top
Cabot Taps Separation Project – Greenfield, Montague
EEA # 15212
Issued July 18, 2014
Secretary’s Certificate (pdf)
Requires an Environmental Impact Report
Submitted June 11, 2014
Environmental Notification Form (pdf)
Comments due July 11, 2014
For copies: Paul Knapik (508) 792-4534
MEPA Analyst: Alex Strysky (617) 626-1025
return to list of projects or return to top
Belchertown State School Redevelopment Project – Belchertown
EEA # 15198
Submitted November 23, 2015
Draft Environmental Impact Report
Comments due December 23, 2015
Record of Decision
Secretary has granted a Phase 1 Waiver (pdf)
Issued July 11, 2014
Issued June 13, 2014
Secretary’s Certificate (pdf)
Requires an Environmental Impact Report
Submitted May 7, 2014
Environmental Notification Form (pdf)
Comments due June 6, 2014
For copies: Holly Carlson (978) 897-7100
MEPA Analyst: Alex Strysky (617) 626-1025
return to list of projects or return to top
MGM Springfield – Springfield
EEA # 15033
Issued November 25, 2015
Secretary’s Certificate (pdf)
Does not require an Environmental Impact Report
Submitted November 9, 2015
Notice of Project Change (pdf)
Comments due November 18, 2015
Issued December 31, 2014
Secretary’s Certificate (pdf)
Adequately and properly complies with MEPA
Submitted November 24, 2014
Final Environmental Impact Report (FEIR) (no link provided, call for a copy)
Comments due December 24, 2014
Issued February 7, 2014
Secretary’s Certificate (pdf)
Adequately and properly complies with MEPA
Submitted December 18, 2013
Draft Environmental Impact Report (DEIR) (no link provided, call for a copy)
Comments now due January 31, 2014
Issued May 24, 2013
Secretary’s Certificate (pdf)
Requires an Environmental Impact Report
Submitted March 20, 2013
Environmental Notification Form (pdf)
Comments due April 9, 2013
For copies: Corinne Snowden (978) 897-7100
MEPA Analyst: Holly Johnson (617) 626-1023
return to list of projects or return to top
The Secretary of Environmental Affairs accepts written comments on projects currently under MEPA review. Comments may be submitted electronically, by mail, via FAX, or by hand delivery. Please note that comments submitted on MEPA documents are public records.
Be sure to include the EOEA number on all comments!
The mailing address for comments is:
Secretary Matthew Beaton
Executive Office of Energy and Environmental Affairs (EEA)
Attn: MEPA Office
[Analyst Name], EEA No. _____
100 Cambridge Street, Suite 900
Boston MA 02114
Be sure to include the EOEA number on all comments!
State email addresses are usually: first name.last name @state.ma.us
for example: Aisling.Eglington@state.ma.us
How to Submit Comments to MEPA (this link takes you to the MEPA Site)